A K-12 building with a full size gym and cafeteria. The framed structures for both projects were designed with structural wood bearing construction with wood floor and roof trusses. Both projects were 65,000 to 75,000 sq ft. The project was completed in 8 weeks which was 3 weeks ahead of schedule. The General Contractor on site was Bouma USA management